This blog has discussed both implied-in-fact contracts and express contracts in previous blogs. In a recent appeal at the Armed Services Board of Contract Appeals (“Board”), the Board denied the appeal of two claims, one of which was a delay claim and the other a quantum meruit claim for breach of an implied-in-fact contract.  Lucy Mechanicals, Inc., ASBCA No. 63153, June 4, 2024.

Lucy alleged that the Corps of Engineers breached a task order contract when it failed to deliver certain safety cables, thereby causing it to delay delivery and therefore Lucy had to submit a delay claim to the Corps (i.e. delay based on late Government Furnished Equipment).  However, the government and Board pointed to a release signed by Lacy which was never abandoned by the Government. That was Count I of the Appeal, and Lucy lost Count I.

Count II of the appeal was based on Lacy’s quantum meruit theory which was that an implied-in-fact contract existed here because Lacy had to halt performance, demobilize and later return to complete the work.  The Board noted that recovery under quantum meruit is typically based on an implied-in-law contract which the Board lacks jurisdiction over.  However, an appellant may use quantum merit of damages for an implied-in fact contract, which the Board does have jurisdiction over.

The Board noted that Lacy was pursuing Count I based on an express contract and Count II based on an implied-in-fact contract.  The Court of Appeals for the Federal Circuit has explained that the existence of an express contract precludes the existence of an implied-in-fact contract dealing with the same subject matter, unless the implied contract is entirely unrelated to the express contract.

The Board held that the contract here required cable removal and replacement at one location. Lacy could not argue that the “supplemental effort” of demobilization and remobilization to perform the removal and replacement at the same location was entirely unrelated to the fixed price contract requiring Lacy to complete the exact same work.  The Board therefore dismissed the entire claim

Takeaway. Remember, the existence of an express contract precludes the existence of an implied-in fact contract for the same subject matter, unless the two are entirely unrelated.

By Richard D. Lieberman, Consultant

For other helpful suggestions on government contracting, visit:
Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

Related Post

Season 11: Episode 25: FAR Facts

Hello and thank you for joining us for Episode 24 of Fun with the FAR Season 11! Our next episode will cover FAR Part 49 (Terminations of Contracts)! As we prepare for our 25th episode of Season 11, here are a few Episode 25 FAR Facts for us to think about: Note that...

Evaluation Criteria vs. Solicitation Instructions

A recent bid protest at the Government Accountability Office (“GAO”) reinforces the idea that there is a big difference between evaluation criteria in a solicitation, and instructions in the solicitation on how to prepare an offer.  Tech Systems, Inc., B-421838.3,...

Season 11: Episode 24: FAR Facts

Hello and thank you for joining us for Episode 23 of Fun with the FAR Season 11! Our next episode will cover FAR Part 45 (Government Property), Part 46 (Quality Assurance), and Part 47 (Transportation)! As we prepare for our 24th episode of Season 11, here are a few...