SUM CERTAIN NOT NEGATED BY LANGUAGE TO PREVENT DOUBLE COUNTING

Readers know that to provide a complete claim, one of the elements is that the contractor provide a “sum certain” for the dollar damages that are sought.  You cannot qualify the sum by stating that it is “approximate” or “about” since that is not a certain sum.  But what if you explain in your claim that the sum stated could be changed if there are other payments made, i.e., there may be some double counting.  A4 Const. Co, Inc., ASBCA Nos. 63252,  et al provides the answer.

A4 Const. received a copy from the Army Corps of Engineers (the “Corps”) for design and construction of a special operations mountaineering facility at Fort Carson Colorado.  A4 submitted a claim for four separate items (COVID related price increases, Extra work and differing site conditions, jobsite flooding, and other increases. These separate claims were consolidated in this case.

The Government moved to dismiss the contractor’s appeal of the Corps’ claim denial, asserting that  A4’s overall claim failed to meet the sum certain requirement. The Corps’ pointed to a footnote whereby A4 stated that the claimed amount should be adjusted as needed to avoid a double payment if the Corps pays some of the claimed subcontractor costs to the bonding company that subsequently pays the subcontractor directly.  The Corps asserted that this qualifying language prevented the number from being a sum certain.

The Board rejected this motion, and stated that an indication that a claim may need adjusting in the future does not invalidate the sum certain.  That was precisely what A4 did, and A4’s notification of a possible future adjustment to prevent a potential double recovery does not defeat the sum certain requirement. Accordingly the Board rejected the Government’s motion to dismiss all the claims.

However, the Board agreed to dismiss 3 of the claims that were consolidated in this case because they failed to provide a sum certain for each individual claim submission to the contracting officer.

Takeaway.  If you suspect that there will be double counting of the amount in your claim (or some other important future change), you may provide a sum certain that may be modified in the future if that eventuality occurs.  The sum certain may be adjusted.  But be sure that each separate claim includes an adequate notice of the claim amount (i.e., a sum certain).

Related Post

Season 11: Episode 25: FAR Facts

Hello and thank you for joining us for Episode 24 of Fun with the FAR Season 11! Our next episode will cover FAR Part 49 (Terminations of Contracts)! As we prepare for our 25th episode of Season 11, here are a few Episode 25 FAR Facts for us to think about: Note that...

Evaluation Criteria vs. Solicitation Instructions

A recent bid protest at the Government Accountability Office (“GAO”) reinforces the idea that there is a big difference between evaluation criteria in a solicitation, and instructions in the solicitation on how to prepare an offer.  Tech Systems, Inc., B-421838.3,...

Season 11: Episode 24: FAR Facts

Hello and thank you for joining us for Episode 23 of Fun with the FAR Season 11! Our next episode will cover FAR Part 45 (Government Property), Part 46 (Quality Assurance), and Part 47 (Transportation)! As we prepare for our 24th episode of Season 11, here are a few...