Fun with the FAR Part 7

Acquisition plans for other than fixed priced contracts must be approved and signed by a procurement official at least one level above the contracting officer. FAR 7.103(j).

The government’s “acquisition planner” does not need to be the assigned Contracting Officer.

There are 13 key milestones that occur during an acquisition. FAR 7.105(b)(21).

Agency determinations as to whether a function is or is not an “inherently governmental function” are reviewable by the Office of Management and Budget. FAR 7.503(b).

Related Post

Episode 20: Did You Know?

DID YOU KNOW? FAR Part 34.201 requires an Earned Value Management System (EVMS) during development of a major acquisition system. This can be accomplished by using EVMS or Agile Program Management Systems, which are not closely compatible. Since the government often...

Did You Know? Fun with the FAR Session 15

By David Gallacher, Partner, Sheppard Mullin We had a great discussion on Fun with the FAR, Episode 15 on June 2, 2021 with host Steven Daoust discussing FAR Part 25, Foreign Acquisitions, with co-host David Gallacher (partner, Sheppard Mullin). We started talking...

Did You Know? Fun with the FAR Session 12

By Brett Egusa, Senior Legal Editor at Thomson Reuters Today we learned that the Federal Government has many unique and flexible contracting methods that it can use to fulfill special procurement needs. Under FAR 17.1 and 17.2, for example, we learn that the...