CONSTRUCTION CONTRACT DUE DATE IS NOT A WARRANTY BY GOVERNMENT THAT WORK CAN BE COMPLETED BY DUE DATE

By Richard D. Lieberman, Consultant

In a recent case, a construction contractor sought summary judgment on whether the contract’s 365 day performance period was a warranty by the government that the work could have been completed within that time period.  ECC Int’l LLC, ASBCA Nos. 60165 and 60282, June 2, 2020.  ECC had a contract to construct a facility in Afghanistan.

The Armed Services Board of Contract Appeals considered the question and answered with a very clear “no.”  The Board stated that “a due date in a contract is not a warranty by the government that the contract can be performed within the prescribed due date; to the contrary, it is the contractor [that must] presumably [be] aware of the performance requirements and its own capabilities that assumes the risk of performance by the specified due date.”

The Board stated that this was a “long-standing rule,” and entered summary judgment that the contract’s 365-day performance period was not a warranty that the contract work could be completed within that period.  In so doing, the Board rejected the idea that the 365-day performance period was somehow a defective specification or a guarantee that would require granting the contractor more time if the work was not finished by the due date.

Takeaway.  In preparing its bid or proposal, a contractor must carefully examine if it is capable of meeting the delivery date in a contract.  A contractor must assess whether it can meet whatever performance period is stated in the solicitation.  Furthermore, it is the contractor that assumes the risk of meeting that performance date.  This requires careful preparation of bids or proposals.  If the contractor cannot meet the performance date, it should request a change in the solicitation, and if no change is made, not submit a bid or proposal at all.

For other helpful suggestions on government contracting, visit:
Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

Related Post

Season 11: Episode 18: FAR Facts

Hello and thank you for joining us for Episode 17 of Fun with the FAR Season 11! Our next session will cover FAR Part 30 (Cost Accounting Standards Administration), Part 31 (Contract Cost Principles and Procedures), and Part 32 (Contract Financing)! As we prepare for...

No Piecemeal Protests or Protest Development

At the Government Accountability Office (“GAO”) be sure to present all of your facts and arguments at once—do not provide them in a “piecemeal” fashion.  (Piecemeal is defined as “made or accomplished piece by piece in a fragmentary way.  Merriam Webster’s College...