- Under certain circumstances, the Government can authorize a prime contractor to make purchases from subcontractors under the terms and conditions of the subcontractor’s GSA Federal Supply Schedule contract. FAR 51.103.
- Subcontractors must treat any subcontract/order issued by a prime contractor under FAR 51.103 as if it is from the Government under its FSS Contract, e.g., the subcontractor must pay a GSA FSS industrial funding fee based upon the amount of the order.
Episode 20: Did You Know?
DID YOU KNOW? FAR Part 34.201 requires an Earned Value Management System (EVMS) during development of a major acquisition system. This can be accomplished by using EVMS or Agile Program Management Systems, which are not closely compatible. Since the government often...